Updated as of:
|
12/19/19
|
|
|
|
|
|
|
|
|
Trunkline 2019 Pipeline Outage and Maintenance Summary
|
Listed below is a summary of the planned outages that could
affect capacity or impact any receipt/delivery
locations during the TGC 2019 outage season.
This schedule is not a complete list of all outages and is subject to
change as the season progresses to reflect any project delays, cancellations
or additions. Additionally,
anticipated impact and restrictions are subject to change.
*All scheduled dates represent gas days as defined in the Trunkline
Tariff to mean a period of twenty-four consecutive hours, beginning and
ending at 9:00 a.m. (Central Clock Time).
|
* Indicates revision
|
|
|
|
|
|
|
|
|
*Outage Completed
|
|
|
|
|
|
|
|
|
Revised
|
Start Date
|
End Date
|
Prev. Start Date
|
Prev. End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter Impact
|
|
07/10/2019
|
08/24/2019
|
|
|
Ambia
|
100-1 Line
|
Gate Valve
Replacements
|
No Impact to
Shippers Expected
|
None
|
|
07/17/2019
|
08/01/2019
|
|
|
Epps
|
100-3 Line
|
Tool Runs
|
No Impact to
Shippers Expected
|
None
|
|
07/23/2019
|
08/03/2019
|
|
|
Epps
|
100-3 Line
|
Tool Runs
|
No Impact to
Shippers Expected
|
None
|
|
07/20/2019
|
07/25/2019
|
|
|
Independence
|
100-3 Line
|
Hydrotest
|
Collierville -
AOC out of service
|
Location #80074
shut in
|
|
07/30/2019
|
10/21/2019
|
|
|
Epps
|
100-3 Line
|
Recoats - no
outage required
|
No Impact to
Shippers Expected
|
None
|
|
08/26/2019
|
09/26/2019
|
|
|
Tuscola
|
100-1
|
Pipeline Rebore & offset
|
TBD
|
TBD
|
|
09/25/2019
|
09/27/2019
|
|
|
Tuscola
|
Lateral
|
St. Joseph
M&R - Ameren Upgrade
|
No Impact to
Shippers Expected
|
None
|
|
10/09/2019
|
10/09/2019
|
|
|
North Judson
|
Station
|
ESD
|
No Impact to
Shippers Expected
|
None
|
|
08/19/2019
|
10/28/2019
|
|
|
Joppa
|
Lateral
|
McCleansboro M&R Upgrade
|
No Impact to
Shippers Expected
|
None
|
|
11/07/2019
|
11/07/2019
|
|
|
Ambia
|
Station
|
ESD
|
No Impact to
Shippers Expected
|
None
|
|
10/21/2019
|
10/30/2019
|
|
|
Longville
|
200-2 Line
|
Drip Removal;
Pipe Installation
|
Liberty Storage
out of service
|
Location #93084
shut in
|
|
10/14/2019
|
11/01/2019
|
|
|
Johnsonville
|
Station
|
MRTC Upgrade
|
No Impact to
Shippers Expected
|
None
|
|
10/14/2019
|
11/01/2019
|
|
|
Johnsonville
|
Station
|
MRTC Upgrade
|
No Impact to
Shippers Expected
|
None
|
|
12/02/2019
|
12/15/2019
|
|
|
South Texas
|
100-1 Line
|
Anomaly Repairs
|
Pressure reduction
to 80% from Premont to VS 17. VS 17 to VS 18 will be shut in.
|
Please see
critical notice for impacted meters
|